PJM PC/TEAC Briefs: April 30, 2024
PJM presented a change to the scope of a component of its 2022 Regional Transmission Expansion Plan to rebuild the 230-kV Otter Creek – Conastone line to 500-kV. | PJM
May 6, 2024
|
The East Kentucky Power Cooperative presented possible changes to the process for transferring capacity interconnection rights from a retiring generator to a replacement resource.