Maryland has identified 502 potential sites across the state for federally funded 150 kW DC fast chargers to be installed. | Maryland Dept. of Transportation
States File Plans on Deadline for Federal EV Charging Funds
Not all Can Meet FHWA Requirements to Install Chargers Every 50 Miles on Interstates
Every state met the deadline to file their NEVI plans with the FHWA, but many will fall short of meeting the guidelines that the program requires.