Search
April 28, 2024

joint targeted interconnection queue (JTIQ)

Minnesota Solar Energy Industries Association
MISO to Try Again for Interconnection Queue MW Cap, Open Window for 2023 Requests
MISO confirmed it likely will try again with FERC in the third quarter to apply an annual megawatt cap to its interconnection queue.
MISO and SPP
MISO, SPP Ditch 90/10 JTIQ Allocation After $465M DOE Grant
Weeks after the nearly $2 billion Joint Targeted Interconnection Queue (JTIQ) transmission portfolio was awarded a $465 million Department of Energy grant, MISO and SPP are switching their proposed cost allocation for the projects.
© RTO Insider LLC
SPP ‘All Over’ Addressing Resource Adequacy
The Resource and Energy Adequacy Leadership (REAL) Team, a cross-section group of regulators, directors and stakeholders, is the answer to SPP's No. 1 strategic priority: resource adequacy.
Grid Strategies
New Report Finds MISO, PJM Could Save Billions Through Interregional Tx Expansion
A new ACORE report concludes MISO and PJM could save ratepayers $15 billion in a little more than a decade if they build more interregional transmission.
© RTO Insider LLC
OMS Leaders Reminisce on 20 Years at Annual Meeting
OMS took time to celebrate its 20-year anniversary at its annual meeting while exploring familiar themes of restructuring resource adequacy and barriers to large transmission buildout.
SPP
DOE Announces $3.46B for Grid Resilience, Improvement Projects
DOE announced $3.46 billion in funding for grid resilience and improvement projects, including the MISO-SPP joint targeted interconnection queue portfolio.
MISO
MISO Trims Minnesota Line Route in JTIQ Portfolio
MISO has shortened one of the 345-kV lines contained in its $2 billion Joint Targeted Interconnection Queue portfolio with SPP, which will lower costs.
MISO and SPP
FERC Clears MISO, SPP’s Affected System Study Improvements
FERC approved changes to MISO and SPP’s affected system study process to allow either RTO to order upgrades of limiting elements on tie lines.
MISO and SPP
MISO Stakeholders Request JTIQ Cost Containment Measures
Stakeholders asked for cost containment measures for MISO's and SPP’s Joint Targeted Interconnection Queue portfolio after the RTOs said the cost estimate for the projects nearly doubled.
MISO and SPP
JTIQ Portfolio Cost Estimate Nearly Doubles to $1.9B
The cost estimate for MISO’s and SPP’s package of 345-kV lines meant to facilitate the interconnection of generation at the seams has nearly doubled, the RTOs have said in the past week.

Want more? Advanced Search