joint targeted interconnection queue (JTIQ)
MISO confirmed it likely will try again with FERC in the third quarter to apply an annual megawatt cap to its interconnection queue.
Weeks after the nearly $2 billion Joint Targeted Interconnection Queue (JTIQ) transmission portfolio was awarded a $465 million Department of Energy grant, MISO and SPP are switching their proposed cost allocation for the projects.
The Resource and Energy Adequacy Leadership (REAL) Team, a cross-section group of regulators, directors and stakeholders, is the answer to SPP's No. 1 strategic priority: resource adequacy.
A new ACORE report concludes MISO and PJM could save ratepayers $15 billion in a little more than a decade if they build more interregional transmission.
OMS took time to celebrate its 20-year anniversary at its annual meeting while exploring familiar themes of restructuring resource adequacy and barriers to large transmission buildout.
DOE announced $3.46 billion in funding for grid resilience and improvement projects, including the MISO-SPP joint targeted interconnection queue portfolio.
MISO has shortened one of the 345-kV lines contained in its $2 billion Joint Targeted Interconnection Queue portfolio with SPP, which will lower costs.
FERC approved changes to MISO and SPP’s affected system study process to allow either RTO to order upgrades of limiting elements on tie lines.
Stakeholders asked for cost containment measures for MISO's and SPP’s Joint Targeted Interconnection Queue portfolio after the RTOs said the cost estimate for the projects nearly doubled.
The cost estimate for MISO’s and SPP’s package of 345-kV lines meant to facilitate the interconnection of generation at the seams has nearly doubled, the RTOs have said in the past week.
Want more? Advanced Search