PJM’s Market Implementation Committee endorsed an issue charge to explore how dual-fuel gas generators should reflect the downtime needed to switch fuels in their requirement to offer into the energy market.
The PJM Operating Committee endorsed manual revisions that included the elimination of a requirement that actual meter test results should be provided to the RTO.
PJM presented manual revisions to replace its standard for determining whether a resource point of interconnection on a distribution facility falls under federal or state jurisdiction.
FERC approved an agreement between Southern California Edison and Longroad Development Co. regarding interconnection of a 500-MW battery energy storage project, with one commissioner acknowledging Longroad remains “between a rock and a hard place.”
Maryland legislators went down to the wire on their last day of session, passing legislation that aims to bring some relief to utility bills.
Vineyard Wind is asking a court to block its turbine manufacturer from walking away from the nearly complete offshore wind project as the two squabble over hundreds of millions of dollars in cost overruns.
The group developing a new resource adequacy program for non-CAISO members of the ISO’s Extended Day-Ahead Market is soliciting stakeholder participation to develop a proposal.
PJM is to present its initial design for a reliability backstop procurement intended to award multiyear capacity commitments for resources able to enter service within five years to serve large loads.
Former U.S. Rep. Eric Cantor says the "almost ferocious negativity around data centers" is proof that the grid has become politically weaponized.
CAISO’s Extended Day-Ahead Market is on schedule to launch May 1 with PacifiCorp as its first participant, as the new market goes through a third and final phase of parallel operations testing before starting.