Nuclear Power
A common refrain at FERC’s technical conference on the co-location of data centers was that the issue is just part the broader problem of resource adequacy.
FERC rejected an amended ISA filed by PJM to allow an existing data center co-located at a Talen Energy nuclear plant to expand, saying it did not meet the commission's standards for changes from its pro forma rules.
Entergy said it can tackle industrial load growth with new solar, carbon capture technology at new and existing gas plants and by possibly bringing new nuclear capacity into the mix.
Finding the sites and hundreds of megawatts of power data centers is “rather limited,” so said talks at the U.S. Energy Association’s Energy Tech Connect Forum.
NextEra Energy reported deals for 3 GW of new renewables with its third quarter financials and said it has reached a framework agreement totaling 10.5 GW with two major corporations.
Dominion Energy’s 2024 Integrated Resource Plan calls for major expansions of offshore wind, solar power and natural gas to meet surging demand in its territory.
The dispute between Exelon and Constellation Energy continued to play out in FERC, as the latter and others protested a series of filings from the former’s utilities seeking to implement new rules for co-locating data centers at power plants in their territories
Exelon on Sept. 30 filed a petition for a declaratory order from FERC on its dispute with Constellation Energy over the latter’s effort to co-locate major loads at two of its nuclear plants.
Thomas Gleeson, chair of Texas’ Public Utility Commission, spoke at the Texas Clean Energy summit about the challenges he has faced during his tenure.
PJM is trying to figure out how the development of new capacity can be sped up as a growing number of resources have cleared the interconnection queue but not entered commercial operation.