ISO-NE Installed Capacity Requirement Filing Approved
FERC approved ISO-NE’s proposed values for the Installed Capacity Requirement, capability credits and related values in time for the capacity auction.
Invenergy
FERC Ends Clear River CSO, Denies Invenergy Waiver
FERC granted ISO-NE’s request to terminate the capacity supply obligation (CSO) for Invenergy’s delayed 485-MW Clear River Energy Center Unit 1.
Invenergy
ISO-NE Asks FERC to End Clear River CSO
ISO-NE asked FERC to terminate the capacity supply obligation of the Invenergy Clear River Energy Center Unit 1 combined cycle plant in Burrillville, R.I.
FERC Postpones Tech Conference on PJM Regulation Market
FERC agreed to postpone a technical conference over the frequency regulation market in PJM.
AEP
PUCT Briefs: Regulators Begin Addressing Utility Tax Savings
The Texas Public Utility Commission took its first steps in determining how to share federal corporate tax cuts with ratepayers.
Invenergy
ISO-NE Bars Invenergy Plant from FCA 12
ISO-NE has barred Invenergy’s planned Clear River Energy Center Unit 2 from offering into February’s capacity auction because of permitting delays.
Invenergy
Proposed RI Power Plant Loses Cooling Water Source, Seeks Delay
The proposed Clear River Energy Center in Rhode Island has lost its planned cooling water source; Invenergy is asking state siting officials for another month to secure a new one.
After Years of Questions, Interconnection Customers Await Answers
Panelists discussed improving the transmission interconnection process at the Energy Bar Association’s Annual Meeting.
Vermont Green Line Developers Seek New York Permit
Anbaric Transmission and National Grid filed with the New York PSC for their Vermont Green Line.
Prices Down 26% in ISO-NE Capacity Auction
Prices dropped 26% in ISO-NE’s 10th Forward Capacity Auction as new resources more than made up for retiring generation.