Texas RE
Texas RE Endorses 6.4% Budget Increase for 2026
The Texas Reliability Entity’s Member Representatives Committee has unanimously approved the entity’s 2026 budget and business plan that is within 1% of previous projections, but at 6.4% increase over 2025.
ERCOT
PUC Staff Urges Approval of 765-kV Lines to West Texas
The Texas Public Utility Commission’s staff has recommended the commission approve the construction of three 765-kV transmission lines, rather than 345-kV, into the petroleum-rich Permian Basin to improve the region’s reliability.
NERC
Data Centers’ Reliability Impacts Examined at FERC Meeting
FERC heard details about recent reliability incidents caused by data centers tripping offline in Virginia and Texas and NERC's efforts to address them.
Lone Star Industrial Park
2 More Projects Fall out of TEF Loan Program
The troubled Texas Energy Fund has lost two more projects from its original list of applicants, raising questions about its ability to quickly add 10 GW of gas-fired dispatchable resources to the ERCOT grid.
© RTO Insider
GCPA Conference Examines the Biggest Change to ERCOT Market in 15 Years
ERCOT is poised to start testing real time co-optimization of energy and ancillary services in a few weeks and bring the change live this December, which will mark the biggest paradigm shift in Texas' wholesale markets in 15 years.
ERCOT
ERCOT Board of Directors Briefs: April 7-8, 2025
ERCOT’s plans to continue running a 55-year-old San Antonio gas plant scheduled for retirement are being endangered by "pretty significant findings" that increase costs and delay the schedule.
ERCOT
Texas Loan Program Loses 2 More Gas Projects
Texas’ loan program for gas generation has lost two more projects, marking the third and fourth companies to withdraw projects from the due diligence review process.
ERCOT
Texas Groups Ask FERC to Reject Puerto Rican Company Petition for Regulation
ERCOT, Oncor and the Texas PUC asked FERC to deny a petition from Puerto Rican company Pluvia to bring the territory under the commission’s jurisdiction.
ERCOT
ERCOT: 60 GW in Additional Demand by 2031
ERCOT has unveiled a long-term load forecast for 2031 that adjusts projections provided by transmission providers and accounts for the uncertain nature of data centers and other large users.
© RTO Insider
Asthana, Vegas to Headline ERCOT’s Innovation Summit
PJM's Manu Asthana will join ERCOT's Pablo Vegas in opening the Texas grid operator’s second annual Innovation Summit by discussing how they are adapting to and managing the complexities of “rapidly changing grids.”