generation deactivation
PJM plans to modify and refile a proposal to revise how capacity interconnection rights can be transferred from a deactivating resource to a new unit.
PJM’s Kevin Hatch presented an update on how two heat waves between July 14-17 and 23-30 affected PJM operations, which involved multiple demand response deployments and emergency alerts and advisories.
PJM presented manual revisions to reflect the generation deactivation process stakeholders approved in January.
PJM stakeholders have endorsed changes to accounting of demand response in load forecasts, among other actions.
PJM stakeholders delayed voting on five proposals to rework the notification deadlines for generation deactivations and how compensation for reliability-must-run contracts is determined.
Several public interest organizations have filed a complaint with FERC contending PJM’s capacity market inflates consumer prices by not counting generators operating on RMR agreements as a form of capacity.
The Maryland Office of Peoples Counsel and PJM's IMM urge FERC to reject a compensation plan for NRG keeping a portion of its Indian River coal plant open under a reliability contract.
The PJM Planning Committee is considering a change to an issue charge framing a discussion on how capacity interconnection rights can be transferred from a retiring generator to a planned resource in the interconnection queue.
Average load-weighted electricity prices in PJM fell by around half in 2023, the Independent Market Monitor said in its annual State of the Market Report.
PJM presented a quick fix proposal to introduce a new long-term transmission planning approach that includes a longer 15-year horizon and considers state legislation that could affect generator participation in RTO markets.