Leeward Renewable Energy

MISO Plots Filing to Restrict Mid-queue Fuel Swaps
MISO is down to two options to curb generation developers’ ability to change their proposed projects’ fuel type in the interconnection queue.
MISO Moves to Constrain Mid-queue Fuel Changes
MISO is considering how to restrict generation developers’ ability to change the fuel type of proposed projects in the interconnection queue.
FERC: No MISO Rules on Mid-queue Fuel Change Studies
FERC said MISO’s Tariff was silent on the issue of whether a generation project can switch from wind to solar while in the RTO’s interconnection queue.
FERC OKs Most of PJM Order 845 Compliance Filing
FERC largely accepted PJM’s Order 845 compliance filing addressing concerns over a lack of transparency regarding contingent facilities.
FERC Partially Accepts Tri-State Order 845 Filing
FERC partially approved Tri-State Generation and Transmission Association’s Order 845 compliance filing, directing the cooperative to make more changes.
FERC Approves SPS Request to End QF PPAs
FERC OK'd Southwestern Public Service Co.’s request to terminate its obligation to enter into new power-purchase contracts with facilities over 20 MW.