MISO Petitions 8th Circuit in Dispute with SPP over Data Center-strained Flowgate
Proceeding Centers on Congestion Stemming from North Dakota Crypto-mining Facility
May 5, 2025
|
MISO is seeking judicial review of two FERC decisions preventing the RTO from recouping costs or revising a joint procedure with SPP over a shared North Dakota transmission line that has become congested by a new cryptocurrency mining facility.