AESOCAISO/WEIMCAISO Board of GovernorsCalifornia Agencies & LegislatureCalifornia Air Resources Board (CARB)California Energy Commission (CEC)California LegislatureCalifornia Public Utilities Commission (CPUC)EDAMOther CAISO CommitteesWestern Energy Imbalance Market (WEIM)WEIM Governing BodyCompany NewsERCOTERCOT Board of DirectorsERCOT Other CommitteesERCOT Technical Advisory Committee (TAC)Public Utility Commission of Texas (PUCT)FERC & FederalIESOIESO Strategic Advisory CommitteeIESO Technical PanelISO-NEISO-NE Consumer Liaison GroupISO-NE Planning Advisory CommitteeNEPOOL Markets CommitteeNEPOOL Participants CommitteeNEPOOL Reliability CommitteeNEPOOL Transmission CommitteeMarketsAncillary ServicesCapacity MarketEnergy MarketReservesVirtual TransactionsMISOMISO Advisory Committee (AC)MISO Board of DirectorsMISO Market Subcommittee (MSC)MISO Planning Advisory Committee (PAC)MISO Regulatory Organizations & CommitteesOrganization of MISO States (OMS)MISO Reliability Subcommittee (RSC)MISO Resource Adequacy Subcommittee (RASC)NYISONY PSCNYISO Business Issues CommitteeNYISO Management CommitteeNYISO Operating CommitteeOther NYISO CommitteesPJMPJM Board of ManagersPJM Market Implementation Committee (MIC)PJM Markets and Reliability Committee (MRC)PJM Members Committee (MC)PJM Operating Committee (OC)PJM Other Committees & TaskforcesPJM Planning Committee (PC)PJM Transmission Expansion Advisory Committee (TEAC)Public PolicyEnvironmental RegulationsReliabilityState & RegionalAlabamaAlaskaArizonaArkansasCaliforniaColoradoConnecticutDelawareDistrict of ColumbiaFloridaGeorgiaHawaiiIdahoIllinoisIndianaIowaKansasKentuckyLouisianaMaineManitobaMarylandMassachusettsMichiganMinnesotaMississippiMissouriMontanaNebraskaNevadaNew HampshireNew JerseyNew MexicoNew YorkNorth CarolinaNorth DakotaOhioOklahomaOntarioOregonPennsylvaniaRhode IslandRTO-IndianaSouth CarolinaSouth DakotaTennesseeTexasUtahVermontVirginiaWashingtonWest VirginiaWisconsinWyomingResourcesDemand ResponseDistributed Energy Resources (DER)Energy EfficiencyEnergy StorageBattery Electric StorageOther Electric StorageGenerationCoalGeothermalHydrogenHydropowerNatural GasNuclear PowerOffshore WindOnshore WindOperating ReservesRooftop/distributed SolarUtility-scale SolarResource AdequacySpecial Reports & CommentaryCommentaryConference CoverageOther CoverageSpecial ReportsSPPMarkets+Other SPP CommitteesSPP Board of Directors & Members CommitteeSPP Markets and Operations Policy CommitteeSPP Regional State CommitteeSPP Seams Advisory GroupSPP Strategic Planning CommitteeWestern Energy Imbalance Service (WEIS)SPP/WEISTransmissionFinancial Transmission Rights (FTR)Transmission OperationsTransmission PlanningTransmission Rates
Capacity auction reforms, a new asset condition reviewer role, parallel transmission planning efforts, new reserve products, Pay-for-Performance changes and interconnection modifications are likely to be on the docket for ISO-NE in 2026.
FERC terminated a show-cause proceeding against SPP and accepted the RTO’s proposal to revise its collateral requirements for financial transmission rights by including an additional re-marking mechanism for seasonal products.
A California PUC judge has proposed the commission order an additional 6 GW of capacity for the state between 2029 and 2032 to get ahead of disappearing federal tax credits and loans for renewable energy resources.
Texas regulators have approved the first transmission project in the Permian Basin Reliability Plan, along with several other projects.
NV Energy notified the Public Utilities Commission of Nevada that it plans to leave the Western Power Pool’s Western Resource Adequacy Program, citing five critical issues with the program’s design.
The U.S. Department of Energy has terminated 321 grants totaling $7.56 billion for 223 projects, apparently targeting Democratic-leaning states.
Xcel Energy is fighting two counties that are blocking a segment of the company’s Colorado’s Power Pathway transmission project.
Duke Energy filed its long-range plan with the North Carolina Utilities Commission, calling for more natural gas-fired generation and batteries while keeping existing coal plants online to meet accelerated demand for electricity.
Inflation and higher borrowing costs pushed MISO’s cost of new entry up by about 5% heading into the 2026/27 planning year, but stakeholders are questioning MISO’s use of 2020 data in calculations in order to keep prices lower.
FERC issued a final rule and related Notice of Proposed Rulemaking on Oct. 1 to start “sunsetting” 53 regulations in response to an executive order from President Donald Trump.