AESOCAISO/WEIMCAISO Board of GovernorsCalifornia Agencies & LegislatureCalifornia Air Resources Board (CARB)California Energy Commission (CEC)California LegislatureCalifornia Public Utilities Commission (CPUC)EDAMOther CAISO CommitteesWestern Energy Imbalance Market (WEIM)WEIM Governing BodyCompany NewsERCOTERCOT Board of DirectorsERCOT Other CommitteesERCOT Technical Advisory Committee (TAC)Public Utility Commission of Texas (PUCT)FERC & FederalIESOIESO Strategic Advisory CommitteeIESO Technical PanelISO-NEISO-NE Consumer Liaison GroupISO-NE Planning Advisory CommitteeNEPOOL Markets CommitteeNEPOOL Participants CommitteeNEPOOL Reliability CommitteeNEPOOL Transmission CommitteeMarketsAncillary ServicesCapacity MarketEnergy MarketReservesVirtual TransactionsMISOMISO Advisory Committee (AC)MISO Board of DirectorsMISO Market Subcommittee (MSC)MISO Planning Advisory Committee (PAC)MISO Regulatory Organizations & CommitteesOrganization of MISO States (OMS)MISO Reliability Subcommittee (RSC)MISO Resource Adequacy Subcommittee (RASC)NYISONY PSCNYISO Business Issues CommitteeNYISO Management CommitteeNYISO Operating CommitteeOther NYISO CommitteesPJMPJM Board of ManagersPJM Market Implementation Committee (MIC)PJM Markets and Reliability Committee (MRC)PJM Members Committee (MC)PJM Operating Committee (OC)PJM Other Committees & TaskforcesPJM Planning Committee (PC)PJM Transmission Expansion Advisory Committee (TEAC)Public PolicyEnvironmental RegulationsReliabilityState & RegionalAlabamaAlaskaArizonaArkansasCaliforniaColoradoConnecticutDelawareDistrict of ColumbiaFloridaGeorgiaHawaiiIdahoIllinoisIndianaIowaKansasKentuckyLouisianaMaineManitobaMarylandMassachusettsMichiganMinnesotaMississippiMissouriMontanaNebraskaNevadaNew HampshireNew JerseyNew MexicoNew YorkNorth CarolinaNorth DakotaOhioOklahomaOntarioOregonPennsylvaniaRhode IslandRTO-IndianaSouth CarolinaSouth DakotaTennesseeTexasUtahVermontVirginiaWashingtonWest VirginiaWisconsinWyomingResourcesDemand ResponseDistributed Energy Resources (DER)Energy EfficiencyEnergy StorageBattery Electric StorageOther Electric StorageGenerationCoalGeothermalHydrogenHydropowerNatural GasNuclear PowerOffshore WindOnshore WindOperating ReservesRooftop/distributed SolarUtility-scale SolarResource AdequacySpecial Reports & CommentaryCommentaryConference CoverageOther CoverageSpecial ReportsSPPMarkets+Other SPP CommitteesSPP Board of Directors & Members CommitteeSPP Markets and Operations Policy CommitteeSPP Regional State CommitteeSPP Seams Advisory GroupSPP Strategic Planning CommitteeWestern Energy Imbalance Service (WEIS)SPP/WEISTransmissionFinancial Transmission Rights (FTR)Transmission OperationsTransmission PlanningTransmission Rates
MISO opened another review of a second project from its first long-range transmission plan portfolio, prompted again by construction cost overruns.
Louisiana-based power generator Pelican Power is the first to register a complaint over MISO’s yearslong miscalculation in its capacity auctions in an effort to stop the RTO’s retroactive pricing corrections.
A federal judge ruled that President Donald Trump’s executive order halting onshore and offshore wind power leasing and permitting was unlawful, finding that it violated the Administrative Procedure Act.
Northeastern power systems cannot afford to drop offshore wind if they are to maintain reliability, reduce emissions and lower electricity prices, according to a new analysis from Charles River Associates.
Supreme Court justices appeared ready to overturn a 90-year precedent that has limited presidents' authority to fire members of independent regulatory agencies like FERC.
PJM’s forecasting of hourly peak loads continued to improve in November, with an error rate of just 1.17%, staff told the RTO’s Operating Committee.
Among other issues, PJM presented a quick fix proposal to address instances in which offline generators are committed as secondary reserves and granted lost opportunity cost credits.
The SPP leadership team responsible for strengthening the grid operator’s resource adequacy construct and recommending policy directions closed out 2025 by endorsing two protocol changes related to demand response and the cost of new entry.
IESO says record-high clearing prices in its capacity auction will have little impact on ratepayers because the ISO's medium- and long-term procurements play a larger role in the region’s resource adequacy.
NextEra Energy’s annual investor event featured a goal to power 15 to 30 GW of data center hubs by 2035 and a series of nearer-term agreements in the technology sector.