FERC has approved a settlement between ReliabilityFirst and AES Indiana carrying a $90,000 penalty for violations of NERC reliability standards, along with a separate settlement between SERC Reliability and the U.S. Army Corps of Engineers Savannah District that will not require any payment.
NERC submitted the settlements to FERC Jan. 29 in its monthly spreadsheet notice of penalty (NP26-4), along with a separate SNOP detailing violations of the ERO’s Critical Infrastructure Protection standards. Details of the CIP violations, including the utilities and regional entities involved, were not disclosed.
The ERO’s Jan. 29 filing also included two violations involving SERC and the USACE Mobile District but, in errata filed Feb. 18, NERC withdrew those infringements from the SNOP without providing a reason.
AES Indiana’s settlement with RF covers two violations of VAR-002-4.1 (Generator operation for maintaining network voltage schedules). Requirement R1 of the standard requires that generators connected to the electric grid be operated in automatic voltage control mode, with automatic voltage regulator in service and controlling voltage, unless exempted by the transmission operator. Requirement R3 mandates that generator operators notify transmission operators of any change in reactive capability within 30 minutes of becoming aware of it.
The utility informed RF of its violation via a self-report submitted July 26, 2022, in connection with its Eagle Valley generating station. AES reported that the plant’s two gas turbines had not operated in AVC mode between May 2020 and April 2021, when the generating plant entered a planned outage.
Upon investigation, AES found that the gas turbines’ operators had changed their exciter controls to volt-ampere reactive (VAR) mode without informing the TOP. In addition, the plant’s steam turbine generator had also operated in VAR mode from April 2018 — its date of commercial operation — to April 2021. When the plant re-entered operation, all three generators were set to AVC mode and the TOP was notified. AES Indiana conducted an extent of condition review and found no other instances of noncompliance at the Eagle Valley station or any other generating facilities.
RF attributed the root cause of the violation to ineffective training and deficient procedures. The RE wrote that the utility “did not effectively train its operators” on identifying when the voltage regulator was in AVC mode as opposed to any other control mode, or on the need to notify the TOP of any changes in a timely fashion. AES Indiana’s VAR-002 procedure was also not clear enough on the need to operate with the regulator in AVC mode at all times, RF wrote.
The RE assessed both violations as a moderate risk, observing that the incidents were isolated to the Eagle Valley station, which “is located in an area with heavily networked 345/138-kV substations and an adjacent generator plant, which reduces the likelihood of voltage swings or thermal issues.” Against this, RF pointed out that the misoperation continued for multiple years, and AES Indiana discovered the violation only after returning from a prolonged planned outage, rather than because of internal controls.
AES Indiana’s mitigating actions included retraining all Eagle Valley board operators and supervisors on the VAR-002 standard, plant procedures and voltage schedule; implementing quarterly review requirements; and installing conspicuous signage to remind operators of the correct operating mode and the need to remind TOPs of any changes.
No Penalty for USACE-Savannah
The settlement between USACE-Savannah and SERC concerned PRC-005-6 (Protection system, automatic reclosing and sudden pressure relaying maintenance), requirement R3 of which sets the minimum maintenance activities and maximum maintenance intervals by which generation owners and transmission owners must maintain their protection system components.
USACE-Savannah notified SERC in December 2023 that it had failed to complete required maintenance activities for 83 out of 215 protective relays at three generation stations within the required six-calendar-year cadence; at the time, the longest lapse was at the utility’s Thurmond station, where the maintenance should have been completed by December 2021. USACE-Savannah completed all required maintenance by March 14, 2025. An EOC review found no additional instances of noncompliance.
SERC assessed the cause of the violation as “ineffective preventive controls and insufficient workforce assigned to complete required activities.” The RE wrote that the noncompliance posed a moderate risk. No monetary penalty was assessed because USACE-Savannah is a federal government entity, and therefore immune from such penalties as determined in Southwestern Power Administration v. FERC.
To mitigate the infringement, USACE-Savannah implemented a new quarterly review system to verify adherence to the protection system testing and maintenance schedule, and it addressed the staffing issue by training new engineers to specialize in testing the facilities.
