CAISO’s 2025/26 draft transmission plan proposes more than $1 billion for an infrastructure project that would help power new data centers and other large loads in California’s Silicon Valley.
The $1.4 billion Tesla-Metcalf project is the largest proposed reliability project in CAISO’s 2025/26 proposed transmission plan, which includes a total of 38 projects for about $7 billion.
The Tesla project would add two 230-kV lines in the San Jose area to relieve congestion on existing 230-kV lines and various 115-kV lines. CAISO previously found NERC thermal violations on certain lines in the area.
Pacific Gas and Electric’s territory, which would house the Tesla project, has seen a dramatic increase in data center developer applications over the past year. As of August 2025, PG&E had applications for about 10 GW of new data center load, up from about 5.5 GW at the end of 2024.
Between Q3 and Q4 2025, about 2 GW of data center projects moved into PG&E’s final engineering phase, while an additional 50 MW began construction during that time. (See Data Centers Breeze Through PG&E’s Approval Process.)
The increasing rate of load growth stemming from new data centers, EVs and building electrification is expected to create new challenges for the grid, CAISO said in the draft plan. The ISO’s load is expected to increase by 1.8 GW by 2030 and 4.9 GW by 2040 due to data center growth alone, according to a California Energy Commission study in January.
CAISO’s plan also touched on energy affordability, which has become a primary concern at many California energy agencies this year — especially the state’s Public Utilities Commission.
“We recognize the concerns around electricity affordability and are committed in our annual transmission planning process to find ways to meet system needs efficiently and cost-effectively while also providing the best customer value over the long term,” Neil Millar, CAISO vice president of transmission planning and infrastructure development, said in an April 7 press release.
As part of the plan, CAISO proposed the use of reconductoring to increase transmission capacity without having to construct new lines. Staff landed on 12 reconductoring projects as a cost-effective solution to meet electricity demand forecasts.
The plan also includes the $1.68 billion policy-driven Trout Canyon-Lugo 500-kV line project in Southern California Edison’s region, The project, which consists of a new 180-mile-long line between the Trout Canyon and Lugo substations, is estimated to come online in 2035.
CAISO also proposed canceling the $1.1 billion Del Amo-Mesa-Serrano 500-kV project in SCE’s territory, which had been approved in the 2022/23 transmission planning process. SCE had raised the cost estimate to about $5 billion, and the ISO said the project no longer is required because the area now has enough resources and infrastructure due to an additional 2,000 MW of battery storage added downstream from the previously identified line overloads.
EDF Renewables asked CAISO to consider upgrades in the Fresno area, which could see “massive renewable curtailment” of over 7,000 GWh by 2040, the company said in comments to CAISO.
“This level of trapped generation indicates a severe lack of export capability that cannot be solved by battery storage dispatch alone,” the company said.
CAISO’s Board of Governors plans to vote on the 2025/26 transmission plan at its May 19 board meeting.