Search
December 6, 2025

Focus on AEP Transformer, Prices in Heat Wave Review

An overworked transformer and the mobilization of demand response were the focus last week as members and PJM staff continued to discuss the mid-July heat wave.

PJM officials gave lengthy briefings to the Operating and Market Implementation committees, explaining their decisions to relieve an overload on the AEP transformer in the west and their mobilization of demand response in the PECO and PPL zones in the east.

The RTO said it will create a “Frequently Asked Questions” report to address the many issues raised by its response to the six-day heat wave, which resulted in the fourth-highest peak demand in PJM history on July 18. “We intend to kind of shake the tree” for lessons learned, said Mike Bryson, executive director of system operations.

Among the issues to be reviewed will be interchange volatility, demand response flexibility (lead time, minimum run time, offer price), the quality of generator data and the creation of localized interfaces.

LMP Comparison - July 18, 2013 (Source: PJM Interconnection, LLC)
(Source: PJM Interconnection, LLC)

Several members asked why demand response set real time prices in FirstEnergy’s ATSI control zone July 18 — peaking at about $1,800 — but not in the PECO and PPL zones, where DR also was mobilized. RTO prices hit $465 at 2 p.m. but plummeted to $52 at 3 p.m. before returning to more than $200 between 4 and 6 p.m. (See Imports, Not DR, Caused Heat Wave Price Crash.)

Jason Barker, wholesale market development director for Exelon, said the heat wave highlighted the need for a reserve product that allows the conservative operations employed by PJM dispatchers to be reflected in prices. “It blows our mind that we’re seeing $52 prices when you have gigawatts [of demand response and peakers dispatched] with prices much higher,” he said.

AEP/ATSI

ATSI - South Canton #3 Transformer Timeline Combined for July 18, 2013 (Source: PJM Interconnection, LLC)
(Source: PJM Interconnection, LLC)

AEP’s formerly anonymous South Canton #3 transformer became an unexpected constraint on July 18 although the problem hadn’t been foreseen in PJM’s day-ahead projections, PJM officials said.

The high loads became acute at the transformer because of an unplanned outage of more than 1,500 MW of generation east of the transformer. “If that [generation] had been on line we wouldn’t have had this problem,” said PJM’s Chris Pilong.

Load on the transformer increased steadily from 9 a.m., briefly exceeding its “Normal Limit” of about 1,900 MVA at about 1 p.m.

PJM officials called on demand response in the neighboring ATSI control zone to maintain flows through the transformer.  “It was the biggest bang for your buck,” Pilong said.

Operators also created a temporary interface in the ATSI zone (see map) so that the region had a single LMP reflecting the DR prices.

“It was creating a constraint that accurately reflected the actions the operators took,” explained Adam Keech, director of wholesale market operations.

ATSI Interface Map: July 18, 2013 (Source: PJM Interconnection, LLC)
(Source: PJM Interconnection, LLC)

“The idea is to represent the physical reality that operators were dealing with,” said Stu Bresler, PJM vice president of market operations.

Keech said he wasn’t certain PJM had manual language covering “on the fly” creation of a localized interface. “I’m not sure if we’ve done this before,” he said.

DR Call

While it was the need to unload a constraint that led to the call for DR in the west, it was capacity limits across the system that led to the call for 1,000 MW of DR in PECO & PPL, officials said.

PJM must call for all DR in a zone because its rules don’t allow a call for fractional contributions from zones. “Because it was 1,000 MW we needed we chose PECO and PPL,” Bryson said. “If we needed more we would have called additional zones.”

The Pepco zone was rejected for a DR call because of a water main break in the Washington D.C. suburb of Prince George’s County that threatened to leave thousands without water for days.

If they had to call on demand response again on Friday, Pilong said “we most likely would have looked at different zones from PPL and PECO” because of the annual limits on DR calls for individual providers.

Officials said they expected DR to set energy prices across the entire RTO at their maximum of $1,800. The assumption proved wrong because of an unexpected influx of imports.

RTO LMPs hit $465 at 2 p.m. then plunged to $52 at 3 p.m. before returning to more than $200 between 4 and 6 p.m. The fall in prices came as net interchange jumped from less than 4,700 MW to nearly 7,700 MW.

When the imports arrived, PJM operators unloaded generation that was more expensive.

Keech said 2:40 p.m. to 4:40 p.m. was the minimum run time for demand response. From 4:40 p.m. to 5 p.m., he said, operators discussed whether to release DR.  “We decided we didn’t need DR. We didn’t want $1,800 prices.”

PJM Proposes Streamlined DR Registration

Members Wednesday heard three proposals for streamlining the time consuming and error prone demand response registration process.

Current rules require Curtailment Service Providers to submit customer names to both the Electric Distribution Company and Load Serving Entity. The EDC and LSE have 10 days to approve or deny the registration. If either rejects the application — for example because they were mistakenly associated with the customer — the process has to begin from the start.

PJM presented the Market Implementation Committee with proposed improvements from the Demand Response Subcommittee, which reached consensus on changes for emergency registrations but split over three options for changing economic registrations.

All three proposals remove the LSE from the Relevant Electric Retail Regulation Authority (RERRA) review process and eliminate LSE review of economic registrations for contractual obligations. (PJM said there has never been a denial because of contractual obligations.) All three also continue the EDCs’ review for economic registrations.

Option 2A, which received the most support within the subcommittee, would remove the LSE from economic registration review process.

Option 2B, which would simplify the LSE role and remove the requirement that they approve the registration also had substantial support.

The final option, 2C, which would keep the LSE role only for Day-Ahead registration review, was the least popular.

Negative Dec

Although Option 2A received the most support within the subcommittee, PJM and others were concerned about its handling of negative decs.

Currently, if a customer registers for economic DR and participates in the Day-Ahead market, PJM places a negative dec on behalf of the LSE for any cleared bids to offset the LSE’s demand bid. PJM would no longer place the negative dec under Option 2A.

PJM’s Andrea Yeaton, who presented the issue to the committee, said eliminating the negative dec can make it difficult for PJM to clear the market.

Jung Suh, of Noble Americas Energy Solutions, LLC, said the negative dec also is important to LSEs. “It protects us from financial harm,” he said.

The issue will be brought to a vote at the next MIC meeting.

MIC Corrects Omission in Replacement Capacity Inquiry

The Market Implementation Committee Wednesday revised an issue charge it approved in March, adding a work activity inadvertently omitted from the original.

MIC agreed March 6 to consider changing the rules of the PJM capacity market to eliminate arbitrage opportunities between the Base Residual and Incremental capacity auctions. (MIC to Investigate Arbitrage in Capacity Market)

The issue charge brought to a vote mistakenly omitted a friendly amendment from Dave Mabry, energy management specialist for McNees, Wallace, & Nurick LLC, to include “capacity market costs” in the work activities.

The amended issue charge was approved without opposition.

MIC OKs New Process for Exceptions to Generator Parameters

PJM will add new processes for generators seeking exemptions from operating parameters under changes endorsed by the Market Implementation Committee Wednesday.

PJM’s generation parameters set defaults for different types and sizes of generators. The parameters cover minimum run and down times, maximum daily and weekly starts and turn down ratios (Eco Max/Eco Min). They were initiated in 2008 to ensure lower make whole payments for generators whose entire offers were not covered by Locational Marginal Pricing revenues.

The proposed change, the result of a year-long effort between PJM and the Market Monitor, would create three types of exemptions:

  • Temporary Exception: A one-time exception of 30 days or less.
  • Period Exception: An exception lasting for at least 31 days but no more than one year during the 12 months between June 1 and May 31.
  • Persistent Exception: An exception lasting for at least one year.

The changes will require revisions to Attachment K of the OATT, Schedule 1 of the Operating Agreement and section 2.3.4 of Manual 11: Energy & Ancillary Services Market Operations.

The Markets and Reliability Committee will be asked to endorse the changes at its next meeting. Assuming FERC approval, the changes will be effective Oct. 1.

MIC, OC Review Black Start Manual Changes

The Operating and Market Implementation committees heard first reading last week on proposed manual changes governing PJM’s acquisition and deployment of black start resources.

The revisions conform to proposed Tariff changes developed by the System Restoration Strategy Task Force to increase the pool of potential resources. PJM expects to lose some existing black start capacity by 2015 as a result of the planned retirements of coal-fired generators.

The Tariff changes were submitted to the Federal Energy Regulatory Commission last month (ER13-1911).

Affected are manuals 12 and 27:

  • Section 7 of Manual 27 allows the cost of cross-zonal black start units to be allocated to multiple zones based on transmission owners’ critical load share.
  • Section 4.6 of Manual 12 governs the number of critical units in a zone and the ratio of black start generation to critical load in a zone. It also eliminates a restriction on the number of black start units at a station, allows units to provide service outside their zone and changes the time in which a unit must close to a dead bus.

The MIC will be asked to endorse the changes at its next meeting.

PJM Contact: Tom Hauske

Split Decision for Financial Traders on PJM Line-Loss Collections

By Rich Heidorn Jr.

In a split decision for financial traders, an appellate court Monday sent a dispute regarding PJM’s overcollection of line-loss revenues back to the Federal Energy Regulatory Commission.

The U.S. Court of Appeals for the D.C. Circuit upheld (Case No. 08-1386) FERC’s decision denying financial traders a share of surplus line-loss revenues. But the court ordered the commission to justify its rationale for demanding repayment of $37 million in surplus funds awarded to the traders in 2009.

The money at stake is the result of PJM’s “marginal loss pricing” method for collecting transmission line-loss payments, which treats every transmission as if it were the last transmission in the system. Because this method charges each buyer for the most problematic load transmission at the time, it collects far more than actual losses.

The alternative, average loss pricing, is more accurate in the aggregate, but overcharges loads close to generation and undercharges loads far from generation.  It was outlawed in a 2006 FERC order.

The result of the marginal loss method is “a large pot of money,” as the court described it, with “no clear owner.” About $18 million was overcollected in 2011.

The commission approved PJM’s plan to distribute the surplus to recipients based on their contributions to the transmission system’s fixed costs. The commission said that financial traders – those who make “virtual” trades that are settled financially – had no claim because they do not transmit or take delivery of power.

FERC had ordered PJM not to use the money to “reimburse” market participants for their transmission loss payments, fearing that it would distort trading. The commission said any system that paid virtual marketers according to trading volume would create incentives for them to increase those disbursements by increasing trading volume through uneconomic trades.

The court Monday upheld FERC’s ruling denying virtual traders a share of the surplus, but said the commission had failed to justify its attempt to “claw back” $37 million distributed to the traders in 2009, before the commission changed its position on the matter.

The court said that the disparate treatment of virtual traders was justified because they “perform different roles from load-serving entities within the market and that the system will limit virtual marketers’ incentives to engage in market manipulation.”

But it said FERC had not justified its 2011 decision ordering PJM to “claw back” $37 million awarded to virtual marketers in 2009 for their share of fixed costs paid through up-to-congestion trades.

The court backed the traders’ argument that FERC’s about-face threatened to undermine their confidence in the market.

“In addition to explaining why it should have denied the refunds in the first place, FERC must explain why recouping is warranted. Because FERC failed to explain how it analyzed this crucial aspect of the case, we hold that the Commission acted arbitrarily and capriciously,” the court said. “It may well be that FERC’s policy reasons for effectively ordering recoupment outweigh its negative effects, but FERC must analyze that question, not ignore it. “

The court did not vacate FERC’s recoupment order, however, saying it was “plausible” that the commission could provide a sufficient argument for its decision.

VA OKs Dominion Virginia Power Generator

Virginia regulators last week approved Dominion Virginia Power’s request to build a 1,358 MW natural gas-fired generator near Lawrenceville in Brunswick County.

Dominion said it plans to start construction immediately on the $1.3 billion combined cycle plant, which is expected to go into commercial operation in the summer of 2016.

The Virginia State Corporation Commission approved a Certificate of Public Convenience and Necessity for the project and a rate adjustment clause to recover construction costs. The commission also approved the construction of a 13.5-mile 500 kv transmission line to connect the generator to the grid.

The rate rider will generate $43.5 million in its first year, increasing the monthly bill of a residential customer using 1,000 kilowatt-hours of electricity by 81 cents.

Dominion said the plant, which is being added to serve load growth and replace retiring coal plants, will save $96 million in fuel costs in its first full year of operation.

PJM Abandons Long-term Capacity Effort

PJM members Thursday abandoned a year-long effort to establish a long-term capacity product.

The Markets and Reliability Committee voted to strip development of a “Long-Term Capacity Auction or alternative multi-year mechanism” from the revised charter for the Capacity Senior Task Force.

“We feel that we’ve spent more than enough time on this issue,” said Bill Schofield, representing the PJM Public Power Coalition.

The committee initially rejected the proposed charter, which listed five issues, including two newest problem statements approved in May and June, by a 2.33-2.67 sector-weighted vote.

The committee then approved, by a 3.39-1.61 vote, the charter with the two new problem statements — regarding treatment of demand response as an operational resource and the unit-specific review process under the Minimum Offer Price Rule (MOPR) — but without the long-term capacity issue.

Schofield’s motion to strip the issue was seconded by Jason Barker, of Exelon, while representatives of Pepco and the Maryland Public Service Commission spoke in opposition.

“We think some sort of long-term capacity support is needed,” said Walter Hall, energy market advisor for the Maryland PSC. “We would read [removal] as PJM throwing up their hands.”

Gloria Godson, VP, Federal Regulatory Policy for Pepco Holdings Inc., urged members not to give up on the “thorny issue,” noting that officials in Maryland and New Jersey have attempted to create their own solutions because of PJM’s inability to solve the issue.

“I think the PJM marketplace can resolve that concern. PJM has a lot of smart people,” she said. “We can get a resolution to that issue.”

The task force was created in early 2012 to develop a long-term capacity auction. The issue charge approved by MRC set an August 1, 2012 deadline for filing a proposal with the Federal Energy Regulatory Commission for a long-term auction to provide adequate long-term revenue assurances to support entry of new capacity resources.

In April, the Federal Energy Regulatory Commission approved a tariff change resulting from the CSTF that provides new capacity resources with a mechanism to avoid clearing the capacity auction for one year if they require multi-year price assurance to be a viable project. (See Capacity Market: Three-year Price Guarantee for New Capacity.)

The task force said it would consider whether additional changes are needed after reviewing results of the May auction. While other proposals on the contentious issue have been discussed, none found enough support to win consensus.

In June and August, 2012, the MRC added two items — issues related to demand response providers capacity offers and aligning the capacity market auctions with the regional transmission expansion plan (RTEP) — to the task force’s assignments. In May, the group was tasked with considering revisions to standardize the unit specific review process in the Minimum Offer Price Rule (PJM Demand Response Providers Decry Scrutiny, “Freight Train” of Changes).

It was the latter two issues that led to last week’s charter revision. MRC’s decision to eliminate the task force’s original charge sparked a parliamentary debate with some members saying the committee would also have to vote to eliminate the problem statement. Dave Pratzon, of GT Power Group asked, “Is this a second bite at the problem statement apple?”

MRC secretary Dave Anders said that a vote on the problem statement was not needed.

PJM Seeks to Curb Capacity Auction Speculation

Members voted Thursday to approve a problem statement to consider modifying the design of the Reliability Pricing Model to ensure physical delivery of resources that clear the capacity auction.

Jason Barker, of Exelon, proposed the inquiry, saying it was needed to prevent potential reliability issues because PJM is becoming increasingly reliant on proposed new generation to maintain its reserve margin. Some planned generators that cleared for delivery two years from now “haven’t broken ground yet,” he said.

“While there doesn’t appear to be any reliability threat imminently, we believe this issue is pressing,” he said.

Some players may be speculating without any intention of bringing physical capacity by bidding into the base auction and then buying replacement capacity at a discount in the interim auctions.  Barker said one goal of the inquiry would be to “parse speculation from legitimate covering” of shortfalls and increasing penalties for those who offer capacity resources but fail to produce them in the delivery year.

The problem statement was approved by a 4.15 to 0.85 vote but not before several members expressed concerns over the inquiry.

“We could potentially create more problems than we’re solving,” said Frank Francis, director of regulatory affairs for Brookfield Energy Marketing LP,

Gloria Godson, vice president federal regulatory policy for Pepco Holdings Inc., said her company has legitimate reasons for buying in the incremental auction. “How can you define intent?” she asked.

Dan Griffiths, of demand response aggregator Comverge, said his company doesn’t speculate but needs to use the incremental auction to respond to changes in market rules. “Every year the rules change. That forces us to reevaluate our needs.” “We don’t have regulatory certainty.”

Susan Bruce, an attorney representing the PJM Industrial Customer Coalition, said the initiative should not quash competition: “I want to make sure we are keeping the welcome mat out for new resources and that we don’t discriminate.”

Barker insisted, “It is not our intent to create barriers to competitive entry.”  Any increase in deficiency penalties would apply to all resources, he said.

PJM Executive Vice President for Markets Andy Ott said the issue would be assigned to either the Capacity Senior Task Force or the Market Implementation Committee.

Governor Calls for Maryland RPS, EE Boost

Saying it has a “moral obligation” to do more to combat climate change, Maryland Gov. Martin O’Malley last week called on the state to get one-quarter of its electricity from renewable sources by 2022, a 25% increase from the current Renewable Portfolio Standard.

O’Malley also restated his support for a regional cap-and-trade program to cut carbon dioxide emissions and pledged to improve the state’s lagging energy efficiency programs.

The governor, who will leave office in 2015, wants to strengthen his environmental credentials as he prepares for a possible presidential run.

The state has reduced its greenhouse gas emissions by 8% since 2006. But current efforts are likely to result in only a 17% cut by 2020, short of its 25% reduction target.

Renewable Portfolio Standard

Electricity consumption is responsible for about 41% of the state’s emissions. Thus boosting the RPS goal to 25% would make up a large part of the gap in GHG reductions, O’Malley said.

Renewable power provides almost 8% of Maryland’s electricity, up from less than 6% in 2007. Increasing the state’s RPS targets — currently 18% by 2020 and 20% 2022 — would require the support of lawmakers, who doubled the state’s original RPS goal in 2008.

Doing so would be a boon for renewable generators both in the state and — because the state imports 28% of its electricity — elsewhere in PJM.

Energy Efficiency

The 2008 EmPOWER Maryland Energy Efficiency Act pledged to reduce Maryland’s per capita electricity consumption and peak load demand by 15% below 2007 levels by 2015. Thus far, peak electricity demand has declined by nearly 11% and per capita consumption is down by more than 9%.

More than 430,000 households and businesses have participated in EmPOWER programs, putting the state on track to exceed its 15% peak demand reduction goal. But it is likely to reach only a 14% reduction in per capita usage based on current policies. O’Malley said the state can improve its performance with lessons from states that are reducing consumption faster.

Cap-and-Trade

O’Malley also reiterated the state’s commitment to the Regional Greenhouse Gas Initiative (RGGI). In February, Maryland and the eight other Northeast and Mid-Atlantic states in RGGI pledged to lower their 2014 carbon dioxide emissions to 91 million tons and to reduce the cap by 2.5% annually between 2015 and 2020.

Carbon emissions from power plants subject to RGGI declined from 165 million tons to 92 million tons between 2008 and 2012.  Most of the reduction is the result of the 2008 recession, milder weather and the rise of natural gas at the expense of coal with the remainder coming from energy efficiency and renewable energy programs funded by auction revenues.

O’Malley’s support of RGGI is in contrast with that of New Jersey Republican Gov. Chris Christie, another potential presidential candidate, who pulled his state from the program in 2011, saying it was expensive and ineffective.

O’Malley’s call for an increase in RPS standards also contrasts with the policy of many Republicans. Twenty nine states and Washington, D.C. have RPS standards. In 2011 and 2012, at least 14 states considered 50 bills to lower or weaken RPS standards, five of which succeeded.