Search
December 12, 2025

ISO-NE Proceeding with Shortfall Threshold After Positive Feedback

After receiving positive feedback from stakeholders, ISO-NE plans to proceed with its proposal for a quantitative threshold to determine an acceptable level of energy shortfall risk for the region.

The regional energy shortfall threshold (REST) project is one of the RTO’s key initiatives for 2025 and is intended to establish a threshold reflecting “the region’s level of risk tolerance with respect to energy shortfall during extreme conditions.”

The REST, which incorporates both shortfall magnitude and duration, would be used for seasonal assessments forecasting energy shortfall risks heading into each summer and winter period, along with long-term assessments looking at risks five and 10 years into the future.

When calculating the threshold, ISO-NE would consider the tail 0.25% of 21-day model cases with the most shortfall risk. The REST would be triggered if the average shortfall magnitude of these tail cases exceeds 3% and the shortfall duration exceeds 18 hours. (See “Regional Energy Shortfall Threshold,” NEPOOL Reliability/Transmission Committee Briefs: July 15-16, 2025.)

Jinye Zhao of ISO-NE said at the NEPOOL Reliability Committee (RC) meeting Aug. 19 that, on average, one of the extreme 21-day cases would occur “approximately once every 90 three-month periods.” Accepting this threshold means that “about once every 90 three-month periods, the region can tolerate up to 3% of unserved load on average across the 72 most severe hours.”

“Stakeholders have generally expressed support for the ISO’s proposed tail α% of 0.25%, proposed shortfall magnitude threshold of 3%, and proposed shortfall duration threshold of 18 hours,” Zhao said. “As a result, the ISO has retained its REST proposal as introduced at the June RC.”

Zhao clarified that the duration metric will evaluate the cumulative shortfall hours within a 21-day period instead of the longest period of consecutive shortfall hours. She said focusing on consecutive shortfall hours would introduce significant noise to the data, as small gaps between shortfall periods could mask the length of shortfall events.

She noted that ISO-NE never has experienced load shed due to a lack of generation, so it is not possible to back-test these thresholds for accuracy. However, she stressed that the lack of energy shortfall events in the past does not guarantee a risk-free future, and the increasing uncertainties stemming from climate change and a shifting resource mix and load profile could increase risks.

ISO-NE has said the REST will be a key tool to help identify when solutions are needed, but it is “premature to calculate the value of lost load (VOLL)” associated with extreme shortfall periods, Zhao said.

“While there are methodologies available to calculate metrics like VOLL, applying them may be more appropriate if a specific system risk has been identified through the long-term or seasonal assessment process,” she said. “A cost/benefit analysis could be helpful at that time to evaluate whether potential risk mitigation options are economically justified once the nature and scale of tail risk are identified and better understood.”

Some stakeholders urged the RTO to start thinking about how to identify and pursue solutions if the REST is violated, noting that, if the region identifies significant risks in one of the initial REST analyses, it likely would take years to establish a process for selecting a solution, work through the process and ultimately develop the selected project.

ISO-NE plans to run the REST analysis in conjunction with its seasonal assessments and will report the summer results in June and the winter results in November. For annual long-term assessments, the RTO plans to begin work in February or March and produce a report in November, beginning in 2026.

Mike Knowland of ISO-NE said the RTO will allow stakeholders to suggest modeling sensitivities to include in REST analyses and that ISO-NE plans to include three to five stakeholder-requested sensitivities in each long-term REST assessment. The RC is scheduled to vote on the REST proposal in September.

State Tx Entity, Regional Markets Feature in Ore. Energy Strategy

The Oregon Department of Energy’s new draft energy strategy points to the importance of new transmission development and expanding electricity markets for meeting the state’s energy goals.

ODOE’s draft Oregon Energy Strategy, released for public comment Aug. 14, sets out recommendations by which the state can meet its greenhouse gas emissions policy objectives, which call for fully decarbonizing investor-owned utility electricity deliveries by 2040 and, by 2050, reducing fuel emissions by 90% and economy-wide emissions by 80%.

“An energy strategy could help align policies and programs; it could help navigate hard decisions with a focus on how to maintain affordability and reliability, [and] keep an eye on economic growth, on advancing equity and maximizing benefits, while minimizing harms,” Edith Bayer, ODOE energy systems senior policy analyst, said during an Aug. 14 call to discuss the draft document.

The wide-ranging strategy document identifies five “pathways” for meeting state objectives, including improving energy efficiency, increasing electrification across the economy, investing in clean electricity infrastructure, using low-carbon fuels in hard-to-decarbonize sectors and strengthening “resilience” throughout the energy system.

A section describing the clean electricity pathway warns that the state presently lacks the infrastructure needed to meet its energy transition goals.

“There is not currently sufficient transmission capacity, generating resources or storage to reliably power Oregon’s future electricity needs, particularly if new data centers come online as quickly as forecasted,” ODOE writes, pointing to the need to prioritize construction of new utility-scale resources, which often take years to site, plan, permit, build and interconnect with the grid.

“Failure to develop sufficient resources will not only threaten system reliability and hinder progress toward Oregon’s clean energy objectives, but will inhibit economic development and discourage new businesses from entering the state,” the report says.

ODOE’s top recommendation for addressing the challenge: establish a state “transmission entity” — one that appears to be modeled on New Mexico’s Renewable Energy Transmission Authority and the Colorado Electric Transmission Authority.

The department says the Oregon entity should be given authority to “identify and designate transmission corridors,” undertake “partial siting and permitting approvals” for projects in the corridors and offer direct financial support “through state bonds for projects that are determined to benefit the public interest.”

“Across the Pacific Northwest, transmission constraints hinder access to least-cost generation and contribute to reliability concerns,” the agency wrote. “Line expansions and additions are not proceeding at the pace or scale necessary to meet Oregon’s policy objectives.”

ODOE said the new entity could help simplify the process of siting and permitting transmission lines that traverse both state and federal jurisdictions, a key challenge in a region in which the Bonneville Power Administration controls more than 70% of the transmission network.

“To reduce this barrier, a new state entity could establish designated corridors for transmission development and obtain limited siting approval for development within the corridor, including development of enhanced, expanded or new transmission facilities but also of storage and electric generating resources,” the report notes. “Having a new state entity pursue limited siting approval for an entire corridor would retain Oregon’s historic focus on robust siting and permitting processes, while enabling individual projects within a given sited corridor to proceed more rapidly than is currently possible.”

Bayer noted the recommendation might resemble an Oregon House of Representatives bill (HB 3628) to establish a state transmission authority that failed to emerge from committee during the 2025 session.

“We hope that the text in the draft report captures the potential value that such an entity could provide, as well as the potential risks,” she said. “There’s near universal agreement in all of our engagement and everything that we heard that transmission is one of the most critical areas to meet our goals of clean, reliable and affordable energy.”

Coordination Through Markets

The strategy document also urges Oregon to step up collaboration with its neighbors, specifically through increased engagement with regional markets and other grid efforts.

ODOE calls out the “billions of dollars” the West has saved through expanded participation in CAISO’s real-time Western Energy Imbalance Market since 2014 and notes the development of the region’s two competing day-ahead markets: the ISO’s Extended Day-Ahead Market and SPP’s Markets+.

“Utilities in the region are moving toward more organized power markets to reduce costs and improve reliability. This is essential to more efficiently utilize existing infrastructure and to benefit from geographic and resource diversity across the region,” the agency wrote.

It said regional diversity will become “increasingly important” as states decarbonize, with a more diversified supply mix allowing load-serving entities to “take advantage of different weather patterns, resource mixes and time zones to integrate more renewable generation while mitigating risks from weather changes, including extreme weather events and wildfires.”

ODOE said movement toward an RTO would be “an important step to improve West-wide coordination and reduce costs for consumers.”

The document mentions also the two efforts managed by the Western Power Pool: the Western Resource Adequacy Program to develop regionwide RA requirements, and the Western Transmission Expansion Coalition to identify cost-effective interregional transmission projects.

“It is important that the state of Oregon engage in these activities to advance state energy policy objectives, ensure that regional activities are consistent with state policy and strengthen Oregon’s cooperation on vital areas including market development, resource adequacy, emissions accounting and transmission planning,” the report says.

The comprehensive strategy document recommends a wide range of additional energy-related actions, including those dealing with the electrification of buildings, transportation and industry; energy efficiency and conservation improvements; developing and expanding adoption of low-carbon fuels; and reducing vulnerabilities in the state’s energy system. It also explores equity issues stemming from the transition to cleaner sources of energy, including jobs impacts.

Calif. Utilities Move Cautiously on Dynamic Pricing

Despite a state mandate to implement dynamic pricing, two of California’s publicly owned utilities told regulators they’re not ready to make the leap to rates that change hourly or more often. 

The two utilities — Sacramento Municipal Utility District (SMUD) and the Los Angeles Department of Water and Power (LADWP) — outlined the challenges of dynamic pricing in reports submitted to the California Energy Commission. 

The reports are intended to show utilities’ compliance with the CEC’s load management standards, which include a requirement to offer customer rates that can respond to hourly or sub-hourly price signals. 

The commission on Aug. 13 approved compliance plans from SMUD and LADWP, as well as from two community choice aggregators: the Clean Power Alliance of Southern California and Ava Community Energy Authority, which serves the East Bay. 

The dynamic pricing requirement is based on the idea that electricity customers can use smart devices, such as thermostats, water heaters and EV chargers, to reduce or shift their electric loads in response to price or other signals. 

In addition to saving money for customers, the rates may encourage the use of energy at off-peak hours, improve grid reliability, decrease the need for new electrical capacity, and reduce fossil fuel consumption and greenhouse gas emissions. 

SMUD, which was the first utility in California to implement time-of-day pricing, said in its plan that it is “fully supportive of the goals of the LMS regulations.” 

“We are focused on scaling up programs, including programs that can help reduce the need to purchase costly resource adequacy and to avoid the need to upgrade neighborhood transformers as EV charging loads grow,” Katharine Larson, SMUD’s regulatory program manager, told the commission. 

But with projected net annual costs of $2.4 million to $3.7 million to implement hourly or sub-hourly pricing, dynamic pricing wouldn’t be cost-effective, SMUD said.  

Customer Interest Uncertain

SMUD was also concerned about a potential lack of interest in such a program. The utility cited its experience with its critical peak pricing (CPP) plan, in which customers agree to pay a higher rate when the utility calls a “peak event” in exchange for discounted rates at other times. 

The peak events can occur at any time of day during the summer and can last from one to four hours. Program participants must allow automatic adjustments of smart devices enrolled with SMUD. 

After two years of active recruitment for CPP, fewer than 700 customers have signed up for the program. 

The commission approved SMUD’s compliance plan with the condition that the utility provides an updated cost-effectiveness analysis for dynamic pricing by August 2028. 

In its compliance plan, LADWP said implementing dynamic rates by the load management standard’s April 1, 2026, deadline wouldn’t be feasible and would cause an “extreme hardship” for the utility. 

LADWP doesn’t have advanced metering infrastructure needed to implement dynamic rates, but its plan includes other programs to encourage customers to shift their loads. Those include an electric vehicle managed-charging program. 

Among the CCAs, Ava said it doesn’t yet have enough information to know whether dynamic rates would be cost-effective or benefit customers.  

Ava said “significant uncertainties exist” regarding the potential for load-shift under dynamic pricing, customer acceptance of a complex new rate and administrative costs of the program. To help answer those questions, Ava is participating in a dynamic pricing pilot program with PG&E. 

Similarly, the Clean Power Alliance plans to participate in Southern California Edison’s expanded dynamic rate pilot through 2027. 

Customizing Compliance

The commission’s vote Aug. 13 follows compliance plan approval for six other utilities in May. The commission will consider plans from another nine CCAs at a future meeting. 

Commissioner Andrew McAllister said CEC staff had done a good job in “almost customizing” the implementation of the load-management standards for each utility, “responding to the realities on the ground.” 

“We have a big, diverse state,” McAllister said. “We’re doing something new; we’re sort of creating a new playing field.” 

The CEC approved an update to its load management standards in October 2022. (See California Moving to Dynamic Pricing for Retail Customers.) 

In addition to requiring dynamic pricing, the update directs utilities to maintain up-to-date rates in a database called the Market Informed Demand Automation Server (MIDAS).  

Utilities also must develop a standard tool to support third-party services’ access to rate information for their customers. The commission voted to extend the deadline for submitting the tool to May 8, 2026. 

NYISO BIC Dissects Power Prices During June Heat Wave

NYISO shared a detailed analysis of New York’s late June heat wave, in which significant operating reserve shortages elevated energy prices.

“We had committed mostly everything that was available on the system, as well as the fact that we went short on reserves throughout the [state] for the peak hour,” Nate Gilbraith, manager of energy market design for NYISO, told the Business Issues Committee on Aug. 13. “That means the day-ahead market did not procure the full 2,620-MW reserve requirement.”

NYISO was short about 300 MW of reserves. The real-time market scheduled energy that did not have a corresponding day-ahead energy schedule to meet the needs because the day-ahead market did not “foresee” scheduling needs, Gilbraith said.

Real-time load exceeded the day-ahead forecast and market expectations. Imports from other regions, also affected by the heat wave, were much lower. Some generators experienced outages and derates, with some of those because of the heat wave. Actual load increased real-time market needs by over 900 MW. (See NYISO Issues Energy Warning as Heat Wave Boils New York.)

“What I am hearing you say is, as a consequence of having a tighter system, [reserves] aren’t there anymore as something that can be grabbed when you need them,” said Doreen Saia, chair of Greenberg Traurig’s energy and natural resources practice. “So we need to be much more purposeful when we’re looking at the day-ahead forecast.”

“I’ll say it back to you in another way: I think we need to make sure our operators have the tools to ensure reliability in real time,” Gilbraith said. “The fact we came out of the day-ahead market a bit short raises some questions … with how we set our market rules.”

In some areas, transmission flows met or exceeded facility ratings, causing transmission shortage pricing to occur. This was particularly acute on Long Island, where congestion exacerbated already high statewide prices. On June 24, during the peak evening hours, statewide prices were $2,000 to $3,000/MWh. On Long Island, prices exceeded $7,000/MWh.

A stakeholder asked whether there was more information on how much behind-the-meter solar and special-case resources contributed to load reduction. Gilbraith said that beginning at 6 p.m., BTM solar dropped off very rapidly and so did not contribute as much. Additional analysis of SCRs will be forthcoming, he said.

Stakeholders also asked why neighboring regions did not provide imports as expected. This was in part because the weather was much hotter than forecasted across multiple footprints.

“What we saw on this day was really across the entire Eastern Seaboard,” Gilbraith said. “So everyone is now in a situation where they do not have their reliability reserve requirements. … It was one of those emergency drills that we run through that you don’t ever want to actually be in.”

July Market Performance

NYISO also presented its July market performance report to the committee. The locational-based marginal price for July was $78.89/MWh, higher than the $58.96/MWh seen in June and far higher than the $47.42/MWh seen in July 2024.

Natural gas prices and distillate prices were both higher than in June. This was the largest driver of price increases in New York, according to the ISO.

NYISO noted that for the past couple of months, there have been overestimations in BTM solar forecasts relative to the actual power they provided. Some of this is because of smoke from the Canadian wildfires. The ISO is working on figuring out how much of the overestimation is from the smoke compared to forecasting issues.

FERC Approves Cost Allocation for Eddystone Emergency Order

FERC on Aug. 15 approved PJM’s proposal for allocating the costs for Constellation Energy to continue operating its Eddystone Generating Station near Philadelphia under an emergency order by the U.S. Department of Energy (ER25-2653).  

The cost would be spread across all PJM load, with charges determined by multiplying load-serving entities’ share of the RTO monthly unforced capacity obligation by the monthly credit paid to Constellation. The costs to be included in that credit are subject to review by the Independent Market Monitor. The actual costs will be determined through the deactivation avoidable cost credit (DACC), which was designed for resources whose deactivation is being voluntarily delayed while transmission upgrades are built to allow the resource to go offline without reliability issues. (See PJM Board Selects Cost Allocation for Eddystone.) 

The revisions to the Reliability Assurance Agreement (RAA) are only applicable to the Federal Power Act Section 202(c) order keeping Eddystone online from June 1 to Aug. 28. Any DOE orders pertaining to other resources or to further keep the plant online would require a separate cost allocation filing. 

Several public interest organizations protested allocating the Eddystone costs to all PJM load, arguing that the RTO’s capacity market procured sufficient capacity to cover the 90 days the emergency order is in effect. They wrote that the order itself stated that there is a shortage of capacity in pockets of PJM, quoting its finding that “an emergency exists in portions of the electricity grid operated by [PJM] due to a shortage of facilities for the generation of electric energy, resource adequacy concerns and other causes.” Without further clarification from DOE, they argued, any cost allocation would be arbitrary. 

The protest was signed onto by the Environmental Law and Policy Center, Natural Resources Defense Council, Sustainable FERC Project, Sierra Club, Public Citizen, Citizens Utility Board of Illinois and Environmental Defense Fund. They wrote that PJM continuing to export while operating Eddystone during the heat wave in late June shows that the plant is not needed to maintain reliability and the parties benefiting from its continued operation may not be PJM load. 

“In sum, PJM’s proposal asks ratepayers across PJM to pay for something — resource adequacy — they have already paid for once. PJM ratepayers have no need for, and will not materially benefit from, additional generating capacity. PJM’s dispatch of Eddystone during a recent summer heat wave only raises more questions about the beneficiaries of the unit’s retention,” the organizations wrote. 

PJM defended its RTO-wide cost allocation by stating that Eddystone is in the PECO zone, which saw no transmission constraints binding in the 2025/26 capacity auction, and arguing that Eddystone’s output is therefore considered deliverable across the RTO. Both Constellation and PJM said Eddystone’s operation during the heat wave corresponded to a maximum generation and load management alert, which is a NERC Energy Emergency Alert level 1 event. 

The organizations also focused on the notion that the agreement between Constellation and PJM to use the DACC to determine recoverable costs does not fall under FERC oversight, arguing the costs associated with Eddystone’s operation should be considered wholesale rates. They noted that PJM’s interpretation of which parties are affected by the emergency order and compensation agreement leaves out LSEs and consumers who may be allocated the resulting costs. 

“In PJM’s view, a Section 202(c) order constitutes a blank check to establish charges that may be passed on to other entities and customers with no opportunity for regulatory review. It ignores the fundamental purpose of the Federal Power Act: to provide a check on private utilities,” they wrote. 

The organizations also took issue with an operating memo in which PJM and Constellation agreed to allowing Eddystone to be dispatched for system restoration and for any costs to provide black start service to be recovered through the proposed structure. They argue that would saddle all PJM customers with the cost to provide a localized service, which itself already has a FERC-approved cost allocation. 

The PJM Industrial Customer Coalition submitted comments supporting the cost allocation proposal but argued that the RTO should be required to file the DACC compensation for FERC approval. 

PJM argued that Section 202(c) does not require commission involvement in determining compensation unless the parties involved cannot agree on a methodology. It pointed to San Diego Gas & Electric, in which DOE used Section 202(c) to order CAISO to purchase energy from the spot market; when CAISO sought refunds for the transactions, the commission found that it did not have oversight, as the parties to the sale had agreed to the price. 

FERC found that the cost allocation appropriately matches the scope of the emergency identified by DOE. The commission also determined that the emergency order does not require PJM to demonstrate that ratepayers will benefit from Eddystone’s operation and said that the compensation methodology itself is out of scope. 

“We agree with PJM that the proposed cost allocation recognizes that the emergency order is based on the overall resource adequacy need in the PJM footprint,” the commission wrote. “The emergency order describes an ‘emergency situation,’ referring to PJM’s own public statements and regulatory filings, which reflect a ‘growing resource adequacy concern’ for the entire PJM region. 

“The emergency order also states that the retirement of the Eddystone units would ‘further decrease available dispatchable generation within PJM’s service territory.’ These statements support a finding that the retention of the Eddystone units benefits the PJM region in general.” 

NYISO OC Approves SIS for Micron Fab Interconnection

ALBANY — The NYISO Operating Committee on Aug. 14 approved the system impact study for the second of Micron Technology’s semiconductor chip manufacturing centers slated to begin construction later in 2025 in the town of Clay, N.Y.

Micron’s facilities, also known as fabricators (or “fabs”), are a major contributor to the forecasted load growth in New York state, according to NYISO. This facility, “Fab 2,” will draw 576 MW from the grid. When combined with another fabricator at the same site, the total load will be 1,056 MW. Two other fabricators are also planned at the site over the next 20 years.

Clay is a mostly residential suburb of Syracuse with a population of roughly 60,000, according to census data. Micron’s facility will be the largest electric customer in the town by far. When completed, the chip factory will be the largest manufacturing facility in Onondaga County.

The SIS found that the Micron facility will require upgrades to the local grid. Overloads would occur on several local 245-kV lines and substations, so a new substation will be needed. The study also found voltage transfer degradation, which would require upgrades to nearby interfaces.

National Grid estimated that $139.7 million in network upgrades are required, and the new substation will cost $122.2 million. Other upgrades to nearby transmission interfaces would total about $17 million.

The OC also approved eight SIS scopes, all for data centers spread out across the state. If completed, these data centers would collectively draw over 2,100 MW from the grid.

Kairos Power, TVA Announce Nuclear PPA

The list of firsts for advanced nuclear power grew a little longer Aug. 18 with a power purchase agreement between Kairos Power and the Tennessee Valley Authority. 

The electricity — or more exactly, its clean energy attributes — would be assigned to Google data centers.  

The terms — only 50 MW, not until 2030, from a technology still being developed — are not by themselves a huge splash in a sector that is projecting a need for dozens of gigawatts of capacity in the next five years. 

But it is the first PPA signed by a U.S. utility for the output from an advanced GEN IV reactor, and it is the latest of many indications of the strong interest the tech sector has in next-generation nuclear power, with its promise of emissions-free baseload power and its potential for co-location. 

The PPA between Kairos and TVA would deliver up to 50 MW from Kairos’ planned Hermes 2 Plant to the TVA grid, which powers Google data centers in Tennessee and Alabama. 

It is the first step under Google’s October 2024 agreement with Kairos on a partnership to develop a 500-MW fleet of advanced nuclear reactors by 2035. (See Google, Kairos Sign 500-MW Nuclear PPA.) Kairos will boost Hermes 2’s output from 28 MW to 50 MW to reach the PPA’s terms. 

Kairos is designing a high-temperature small modular reactor fueled with pebble-form TRISO and cooled with low-pressure fluoride salt. 

Hermes 1 is a demonstration reactor under construction in Oak Ridge, Tenn., with an anticipated 2027 startup date. It is intended to produce only heat, not electricity. Lessons learned from Hermes 1 will shape the Hermes 2 demonstration reactor, to be built nearby. (See Kairos Power Cleared to Build Demonstration SMRs.) 

There are two more advanced-nuclear firsts: Hermes 1 was the first GEN IV reactor approved by the Nuclear Regulatory Commission and the first non-light water reactor permitted in the United States in more than half a century. 

Also in Oak Ridge, TVA in May became the first U.S. utility to request a construction permit for a small modular reactor — a GE Hitachi BWRX-300. (See TVA First U.S. Utility to Request SMR Construction Permit.)  

There are many other recent firsts in SMR and advanced nuclear development, but not the most important first: None in this part of the world has entered commercial operation. 

Ontario in May authorized construction for what could be the first commercial SMR in North America. (See Ontario Greenlights OPG to Build Small Modular Reactor.) But the target date for connection to the grid is not until late 2030. 

There is intense interest and effort focused on the development of SMRs, with their promise of faster, less expensive construction. The Nuclear Energy Agency is tracking more than six dozen designs at some stage of development; more than two dozen of the efforts are headquartered in the U.S. 

How many of those efforts obtain sufficient capital and overcome technical hurdles to reach commercial viability remains to be seen. 

The Trump administration is trying to expedite the process, but the 11 projects recently chosen for a fast-track pilot program will receive no financial assistance — only help cutting through regulatory red tape. (See Advanced Nuclear Fast-track Effort Gets First 11 Projects.) 

Nonetheless, advanced nuclear developers often speak with present-tense confidence about their business models and technologies. 

“We build mass-manufactured nuclear plants that will power anything from a data center to a city,” declares Aalo. In fact, Aalo’s liquid-metal reactor design is only in the non-nuclear prototype stage, and the company was a 10-person operation in a coworking space until recently. 

Some of the other companies in the SMR race are not as far along as Aalo. 

Others are steadily moving closer to splitting their first atoms, aided in some cases by the technical and financial resources of the U.S. government.  

In 2021, the U.S. Department of Energy Office of Nuclear Energy put Kairos’ Hermes project on its list of “5 Advanced Reactor Designs to Watch in 2030.” DOE already had begun assisting Hermes financially during the first Trump administration; in 2024 it committed up to $303 million in grants to the effort. 

The cost of developing a first-of-a-kind SMR and bringing a working copy online is considerable — $5.6 billion, in the case of the first Ontario reactor, plus a projected $9.6 billion for the three follow-up SMRs planned on the same site. 

Google, Kairos and TVA said the PPA announced Aug. 18 would help ease some of that first-mover cost and drive down the price tag for future reactors. 

“Google stepping in and helping shoulder the burden of the cost and risk for first-of-a-kind nuclear projects not only helps Google get to these solutions, but it keeps us from having to burden our customers with development of that technology,” said Don Moul, CEO of TVA. 

FERC Partly Grants Complaint on PJM Opportunity Cost Adders

FERC partly granted a complaint from LS Power challenging the PJM calculation of opportunity cost adders (OCA), requiring operating agreement (OA) revisions to more thoroughly document the inputs and algorithms behind the OCA. 

The adder is a component of the cost-based offers that resources submit in the energy market and aims to capture the revenues that may be missed out on if a resource with limited run hours is dispatched when prices are low (EL24-91). The commission wrote that market participants do not have adequate information to determine whether their OCAs are accurate and account for all factors that may limit when a resource can be operated. 

The order requires that market sellers have access to unit-specific inputs, assumptions and results — including intermediate results; a public posting describing the models and algorithms used in the calculator and hypothetical examples showing how they function; and that the Independent Market Monitor and PJM meet with market sellers on request to discuss assumptions built into the calculator and its results. A compliance filing is required within 45 days of the Aug. 14 order. 

“We find that the PJM operating agreement is unjust and unreasonable because it fails to provide market participants with a sufficient level of detail regarding the calculation of OCAs,” the commission wrote. “Inaccurate OCAs that are too low (i.e., do not fully reflect the market participant’s opportunity costs) could cause resources to prematurely use up their limited run hours when energy prices are lower and render them unable to operate in subsequent periods when prices are higher and they are most needed to provide energy and support the bulk electric system’s reliability.  As such, accurate OCAs are essential to help ensure the efficient use of energy-limited resources in PJM, support accurate price formation, and increase market participants’ confidence in and understanding of how market power mitigation provisions are being implemented.” 

The complaint, which was filed in March 2024, argued that the Monitor has not provided enough information on its OCA calculator and market participants are not able to replicate its results. In some cases, LS Power said it has identified issues that have led the Monitor to make changes in how it determines the OCA. Overall, however, it argues the Monitor has not engaged in adequate communication with market participants and has been unwilling to make changes when requested. The complaint also argued that PJM’s decision to eliminate its OCA calculator in June 2020 and instead rely on the Monitor’s calculator should have been brought to the commission as a change to the OA. 

LS Power wrote that only one pollutant was being modeled for its Chambersburg and Rockford generators, causing their adders to be significantly diminished and resulting in the units being prevented from operating during high pricing periods due to emissions limits on their air permits. It estimated the Rockford adder should have been 25 times higher than what the Monitor calculated. After reporting the issue to the Monitor, the company said it was referred to the Manual 15 language detailing the OCA calculation. 

The Monitor responded to the complaint stating that it’s the responsibility of market sellers to submit information about the pollutants that can limit a resource’s run hours and said it met with the company to discuss the adder several times in April, May and June 2022. After additional pollutant data was provided on July 26, 2022, the Monitor updated its modeling of LS Power’s resources. 

LS Power also argued the Monitor was calculating different OCAs for the six units at its Aurora Generating Station, despite each unit being identical. The complaint argued the Monitor has not transparently addressed the cause of the difference. 

While investigating volatility in the adder calculated for a different resource in June 2022, the Monitor said it identified an error in the calculator, where a flaw in the calculation of shadow prices reduced the output that resource was modeled as produced, causing its emissions to vary. The issue was resolved on June 23, 2022, and the Monitor stated there was minimal impact on LS Power’s units. 

In a separate issue, the Monitor said there was an error causing variable operating and maintenance costs (VOM) to be double counted for the Chambersburg generator. This was corrected the same day LS Power raised the issue. The primary issue leading Chambersburg to hit its emissions limit in the period discussed in the complaint was PJM dispatchers using the resource to resolve local constraints. 

The Monitor defended the transparency of the calculator, stating it is adequately detailed in Manual 15 and the only inputs that are not available to resource owners are locational marginal price (LMP) and gas futures, which are proprietary and confidential data provided by a vendor. It stated it has held multiple educational workshops for PJM stakeholders, with materials available online, and will continue to hold more sessions. It also argued PJM can empower third parties, such as the Monitor, to aid in the calculation of market parameters so long as the RTO is the entity implementing them, which the Monitor said is the case here. 

PJM also voiced transparency concerns in its response, stating it has requested access to the software behind the adder, which the Monitor has declined to provide. It supported the Monitor’s role in the OCA calculation, however, stating that PJM staff are the final arbiter of the adder to be included in cost-based offers. 

The RTO engages in annual reviews of the OCA to ensure the process outlined in the OA and Manual 15 is being followed, in addition to periodic review of adders calculated for individual resources to watch for trends and abnormal values. The RTO wrote it has identified instances where it sought further review and was able to request data and meet with the Monitor. 

Responding to LS Power’s request that FERC allow market sellers to propose their own adders, PJM said it already has a pathway for alternatives to be submitted so long as it can be demonstrated the default calculation is not representative of a unit’s opportunity costs. PJM stated it has approved alternative OCAs in the past. 

The commission wrote that more transparency could help identify and resolve the sort of errors the Monitor outlined. 

“The IMM acknowledges that some errors occurred in the calculation of some OCAs. While some of these errors may have been limited in scope, such errors nonetheless harm the efficient functioning of markets and undermine market participants’ confidence that the market rules are being implemented appropriately. There is also the possibility that there are additional issues with OCA calculations that LS Power and other market participants have not been able to identify due to the opaqueness of current OCA calculation process,” the order states. 

The commission declined to require that PJM calculate the OCA, finding that it has remained in control of the implementation of the adders, and declined to require that PJM allow alternative OCAs to be provided by market sellers who cannot demonstrate that the default methodology does not account for some limit. The commission said the issue of PJM having access to the calculator is out of the complaint’s scope but encouraged PJM and the Monitor to collaborate on allowing access. 

FERC Rules Costs of Mich. Coal Plant Extension Can be Split Among 11 States

FERC said MISO should spread the costs of keeping a Michigan coal plant running past its retirement date over the RTO’s entire Midwest region.

The commission issued an Aug. 15 decision on the cost allocation of the J.H. Campbell coal-fired power plant, which is slated to run through Aug. 21 on an order from the U.S. Department of Energy. The plant originally was scheduled to wind down operations May 31. (See DOE Orders Michigan Coal Plant to Reverse Retirement.)

FERC said it’s appropriate that MISO split the costs of running the plant on a load ratio share among local resource Zones 1-7, which includes Wisconsin, Minnesota, the Dakotas, a section of Montana, Iowa, parts of Missouri, downstate Illinois, Indiana and a slice of Kentucky in addition to Michigan (EL25-90).

FERC said the allocation design is in line with its cost causation principle, reasoning that the cost split would “allocate costs in accordance with the scope of the emergency as described by the DOE order.”

“We acknowledge that parties have presented different interpretations of how the DOE order defined the geographic scope of the emergency.  However, we find that the most reasonable reading of the DOE order’s intended scope is that the emergency necessitating the continued operation of the Campbell Plant is in the MISO North and MISO Central regions, i.e., local resource Zones 1-7,” FERC said.

Plant owner Consumers Energy asked the commission for a Zone 1-7 rate recovery, claiming beneficiaries could be found among all Midwestern zones. However, Great River Energy and various public interest organizations argued that load-serving entities in Zones 1-7 already met their resource adequacy requirements, as evidenced by MISO’s 2025/26 Planning Resource Auction and would not benefit from bonus capacity from the Campbell plant. (See MISO Summer Capacity Prices Shoot to $666.50 in 2025/26 Auction.)

Great River Energy argued the DOE mandate focused on the local impacts of generation retirements, which should mean that costs of the plant fall to Michigan’s Zone 7 alone. It said, “allocating costs of complying with the DOE order beyond Consumers’ own load is not supported by the cost causation principle.”

Michigan Attorney General Dana Nessel contended that the DOE order applied to the whole footprint and FERC should order a cost allocation that includes MISO South.

But FERC said it relied on the DOE citing a MISO presentation of the 2025/26 PRA results, where MISO said that “new capacity additions were insufficient to offset the negative impacts of decreased accreditation, suspension/retirements and external resources” in MISO Midwest. The commission said it seemed resource adequacy concerns in the subregion drove the DOE to issue the order.

FERC directed MISO to draft a compliance filing within a month to enact the new allocation. It also told the RTO to define a load ratio share and how it plans to calculate each load-serving entities’ load ratio share.

According to a recent Securities and Exchange Commission filing from Consumers Energy, J.H. Campbell cost $29 million to run from May 23 to June 30. (See DOE Extension of Michigan Coal Plant Cost $29M in 1st Month.)

The commission declined to grant the Organization of MISO States, the Illinois Attorney General and the Illinois Commerce Commission’s request that it instruct MISO to initiate stakeholder discussions on who should foot the bill for the plant’s extension. FERC said further procedure was unnecessary.

FERC also rejected requests to delay its cost allocation decision until rehearing requests on the DOE’s mandate are resolved.

“We find that arguments against adoption of the proposed tariff provision, such as that imposing the costs of keeping the Campbell Plant in operation violates the tariff and the [Federal Power Act] if the DOE order is deemed unlawful are beyond the limited scope of this proceeding and were not referred to the commission by DOE,” FERC wrote.

FERC similarly refused to address the creation of a provision to refund upgrade costs recovered under the cost allocation should the Campbell plant be subject to another stay-open order beyond Aug. 21. It said any such potential procedure was outside the “limited” nature of the allocation docket.

FERC also appeared to cover its bases should the DOE’s order for the coal plant to keep operating not hold up in court.

“While this order approves the cost allocation methodology in the proposed tariff provision, it does not approve recovery of actual costs,” FERC said.

FERC said Consumers Energy needs to petition it in a separate proceeding “at a later date” for approval to recover costs associated with the DOE’s order “before ratepayers can be charged for such costs.”

“Parties may raise issues related to the scope of costs prudently incurred pursuant to the DOE order in that proceeding,” FERC said. It added that parties to the complaint could “take appropriate steps, such as requesting rehearing in this proceeding, to preserve arguments” that FERC should order refunds should the DOE order be modified, or “otherwise revisit its approach to matters that DOE referred to the commission in connection with the DOE order.”

Arizona Renewable Standard on the Chopping Block

Arizona regulators are moving toward the repeal of the renewable energy standard for utilities, saying the mandate has cost ratepayers billions of dollars since it was adopted in 2006. 

The Arizona Corporation Commission voted 5-0 on Aug. 14 to start a rulemaking process to repeal the Renewable Energy Standard and Tariff (REST). 

REST requires 15% of regulated electric utilities’ retail sales to be from renewable resources by 2025. Utilities have met or exceeded the standard. 

Commissioners called REST an outdated mandate that has driven up customer costs. 

“If renewables are truly the most affordable and reliable option … the generational technology should be able to prevail on its own without the need for mandates that have added millions of dollars in extra costs for ratepayers each year,” Chair Kevin Thompson said. 

Commissioner Rachel Walden said the all-source request for proposals process that utilities are required to follow is the best way to select resources. Renewables will continue to be an option, she said. 

“I want to reiterate that if solar and wind is the cheapest generation, and can be balanced out with the reliable baseload, that it will be selected,” Walden said. “I have not heard or seen evidence that there needs to be a mandate.” 

The commission’s action follows a vote in February 2024 to start laying the groundwork for the repeal. (See Tug-of-war Developing over Ariz. Clean Energy Rules.) 

Commission staff will file a notice of rulemaking, and the commission will hold three public comment sessions in November. 

APS’ Clean Energy Goals

The action comes as one major utility, Arizona Public Service, has backed away from its commitment to 100% clean and carbon-free energy by 2050. 

APS also had an interim target of 65% clean resources and 45% renewable energy by 2030. 

During an Aug. 6 quarterly earnings call, officials with APS parent Pinnacle West Capital said the company has updated its clean energy goals to an “aspirational carbon-neutral approach” by 2050. 

The company also is canceling its interim targets “to better reflect APS’ near-term need to ensure reliability and affordability,” Pinnacle West said in a release. The integrated resource planning process will be used “to help determine the most responsible path forward.” 

The company attributed the change to the need for reliable electricity as the state’s population and economy grow at “unprecedented levels.” 

“Our mission is to reliably serve customers at the lowest cost possible,” Pinnacle West CEO Ted Geisler said in a statement. “To do that, we need to integrate the most reliable and cost-effective resources available to us to meet Arizona’s fast-growing energy needs.” 

At the Aug. 14 commission meeting, several speakers said the REST rules should be retained and modernized rather than repealed. 

Autumn Johnson, executive director of the Arizona Solar Energy Industries Association (AriSEIA), said that just because investor-owned utilities have met the 15% renewable energy requirement of REST doesn’t mean they will continue to do so. 

“Given the load growth projected by the IOUs, the plans to spend approximately $5.3 billion on a new gas pipeline and APS’ recent announcement that they are reneging on all of their clean energy goals, there is absolutely no certainty that the utilities will remain at 15%,” Johnson told the commission. 

In an Aug. 7 announcement, the ACC praised the state’s three largest electric utilities for their commitment to Transwestern Pipeline’s Desert Southwest expansion project. The new pipeline will transport natural gas from the Permian Basin in West Texas to Arizona and New Mexico. 

Steven Zylstra, president and CEO of the Arizona Technology Council, said the REST rules have created a predictable framework for private investment in the state’s clean energy economy. 

“With federal renewable and clean energy tax credits already eliminated, now is the worst possible time to undermine an industry that has delivered so much progress for our state,” Zylstra said in comments filed with the commission opposing the repeal. 

REST Costs Disputed

According to the ACC, renewable resources accounted for about 19% of APS’ energy portfolio in 2024, up from 13% in 2023. For Tucson Electric Power, about 29% of its energy portfolio consisted of renewables in 2024, compared to 27% in 2023. 

The ACC estimates the REST rules have resulted in about $2.3 billion in surcharges to Arizona ratepayers since 2006. REST supporters dispute that figure. 

When evaluating costs and benefits, one must consider the cost of non-renewable resources that would have been built without the REST rules, according to comments filed jointly by AriSEIA, Vote Solar and Solar United Neighbors. 

In addition, renewable resources save ratepayers money because they have no ongoing fuel costs, the groups said. 

They noted that 36 states have standards or goals for clean and renewable energy and 21 states have set target dates for achieving 100% clean energy.